Project

Implementation of the Strategic Action Programme for the Bermejo River Binational Basin: Phase II

Key Basin Project Results

1. Development and strengthening of COBINABE as a bi-national entity for management and sustainable development in the Bermejo River Basin. This includes the establishment of a Regional Coordination Committee and a Regional Advisory Committee, development of a communicational Action Program which seeks to promote local stakeholders’ commitment, foster public awareness and build awareness about the benefits of integrated natural resource management, and the training of technicians and managers. 2 Structural measures for the control of erosion and sediment transportation were implemented in the Upper Bermejo Basin, with the active participation of local communities. The works include structural torrent control measures, sediment retention dams, bank protection works, rainwater drainage systems, and consolidation of river channels, among others. 3. A comprehensive environmental information system was launched (SIG Bermejo), integrating actions for the generation, acquisition, processing and storing of information on natural resources in the basin. It consists of a Hydrometeorological Network measuring water level and precipitation, a Hydrosediment Network with information from 40 stations, cartographic information of the Bermejo Basin, statistics on economic data, a Water Quality Monitoring Network, and a Documentation Center, among others.

Results Indicators

Municipal wastewater pollution reduction

[see desc]

INDICATOR#4 (Cleanup of highly impacted water areas) There was an environmental clean-up of the Guadalquivir River which included 1840 meters of collectors in Tomatitas, 29 inspection chambers and 34 house connections; another of the lagoon in San Lorenzo, which contained 2433 meters of sewage, and involved the laying of 3310 meters of pipes for sewer connections; and an infiltration of the Canasmoro field with 229 meters of pipe, 63 septic tanks and 20 latrines. (#176, Bermejo River)
Restored habitat, including wetlands

167 ha

INDICATOR#2 (Consolidating protected areas and protecting biodiversity) A pilot scheme for carbon fixation in the sub-Andean was developed which included the planting of 75 hectares of fruit trees and cedar trees. Activities were carried out in support of the implementation of a Binational Biological Corridor connecting a flora and fauna reserve in Bolivia and two national parks in Argentina to prevent habitat fragmentation and expand the natural resources of the area. In addition, an Action Program for livestock management in the region was outlined. (#176, Bermejo River) INDICATOR#3 (Soil conservation works and water cleanup) There were 11 earth dams and 1 gabion dam constructed in the San Jacinto project area, in addition to the creation of 63 hectares of irrigated farmland, the planting of 10,000 cedar trees and 3,000 fruit trees, and the construction of 130,00 meters of live barriers, 6450 meters of contour levees, 556 meters of channel collectors and 15139 meters of fencing. Soil conservation works and practices (terraces, live barriers, and forest plantations) in the Santa Ana River Basin included incorporation of 93 ha of irrigated crops; 27 gabion dams, 740 m3 of stone cairns, and 2,800 m of enclosures. (#176, Bermejo River)
Catchment protection measures

[see desc]

INDICATOR#1 (Soil management and erosion control in critical areas) The battle to control erosion involved introducing cattle-raising management practices to reduce grazing pressure and erosion control, communal practices regarding grazing land use, protective reforestation, implementation of forest nurseries and waste management in small communities, and the introduction of small-scale erosion and sediment control works, micro-irrigation systems, and sustainable land use and agricultural production practice in Bolivia. Further actions included the creation of 64 gabion dams in the Rio Huasamayo to control flows and protect the right bank, the construction of terrace walls for the consolidation of river channels along the Milmahuasi and Colanzuli rivers, the building of marginal defenses and storm drains for erosion control, and channel control works for riverbed erosion control and sediment retention. (#176, Bermejo River)
Establishment of country-specific inter-ministerial committees

YES

(#886, Bermejo River SAP)
Regional legal agreements and cooperation frameworks

TBD

INDICATOR#2 (Development of a holistic regional legislative, economic, and environmental framework) Environmental zoning developed and implemented as planning instruments for basin management and integrated development; water codes and environmental impact assessment regulations, comparative analyses and recommendations were created; training workshops on the environment and on economic instruments both conducted; pilot territorial zoning plans based on hydrological risk were created for five (5) locations spread across the Upper and Lower Basin.
Regional Management Institutions

YES

Body: Bi-National Commission (COBINABE) GEF Project Result: "INDICATOR#1 (Development and Strengthening of the Institutional Framework) Development and strengthening of COBINABE as a bi-national entity for management and sustainable development; COBINABE’s internal regulations were revised to facilitate and consolidate its capacity as a bi-national entity; more than forty (40) Memorandums of Understanding and Collaboration Agreements were established to facilitate IWRM in the Basin; a Regional Coordinating Committee and Regional Advisory Committee were established to strengthen COBINABE’s coordination; a communicational Action Program for COBINABE was developed and implemented as an institutional identity and communication strategy; COREBE and OTNPB were internally strengthened; at the Argentine provincial level and the Department of Tarija in Bolivia, the powers of governments and civil societies with jurisdiction or interest in the Basin were strengthened." (#176, Bermejo River)
Transboundary Diagnostic Analysis: Agreement on transboundary priorities and root causes
Year: 2000

YES

2000
Development of Strategic Action Program (SAP)

YES

-

Information sources

IWC6 Results Note (2011), GEF3 Tracking Tool (2010)

This project catalyzes the implementation of the Strategic Action Program for the Bermejo River Binational Basin. The project will implement specific strategic activities identified in the GEF-financed strategic action program (SAP), that address the principal root causes of soil degradation as set forth in the transboundary diagnostic analysis (TDA) and, in doing so, will provide the necessary institutional, legal, and informational basis to enhance and restore the environmental functioning of the system, and provide protection to endemic species within the five component ecosystems - montane, humid forest, arid Chaco/savannah, sub-humid Chaco, and humid Chaco. These actions, with increamental costs, will complement Basin-scale interventions by the Binational Commission, and the governments of Argentia and Bolivia, financed in part from national and provincial/prefectural sources and by international loan funding, many of which address expected baseline activities. Strengthening of Basin institutions, building of agency and organizational capacity, and integration of environmental concerns into economic development activites on a sustainable basis, and the promotion of the public awareness and participation are key elements of this project.

Project Category

Other (not set)

Country

Argentina , Bolivia , Regional

Waterbodies

La Plata

Ecosystems

River

Budget

USD 19,770,000

Total Cost of the project

USD 11,040,000

GEF Allocation to project

Partners

UN Environment (UNEP)

To provide leadership and encourage partnership in caring for the environment by inspiring, informing, and enabling nations and peoples to improve their quality of life without compromising that of future generations.

Contacts

Hector Martinez

Technical Coordinator

Enrique Bello

Project Manager

Jorge Rucks

Chief

Gabriel Gaite Uzqueda

Technical Coordinator

Marcela Alicia Di Blasi

Graphic Designer

Carlos Alberto Brieva

Technical Unit staff

Isabelle Vanderbeck
Isabelle Vanderbeck

GEF IW Task Manager (UNEP)

GEF ID

886

Status

closed

Focal Area

International Waters

Project Type

Full-Size Project

Start Date

02 May, 2001

End Date

01 Mar, 2010

Last Update