This report covers the period from 7 August 1995, the official start date of the contract between NRI and UNOPS, and 29 February 1996. This and future progress reports will be kept as concise as possible drawing attention only to those activities and events which have a significant bearing on project progress toward its overall purpose. Inevitably during the start up period of such a large and complex project early progress was intermittent as the various components of the team and its logistical support structure have been brought together in the UK and in the region.

398: Pollution Control and Other Measures to Protect Biodiversity of Lake Tanganyika (LTBP)

19 mar. 2010

Progress Report No. I. Aug 1995 - Feb 1996..pdf

Tanganyika
Report