ceo-endorsement-form-neretva-and-trebisnjica-management-project CEO Endorsement Form - Neretva and Trebisnjica Management Project REQUEST FOR CEO ENDORSEMENT/APPROVAL
PROJECT TYPE: Full-sized Project THE GEF TRUST FUND Submission Date: March 7, 2008 Re-submission Date: April 14, 2008 PART I: PROJECT INFORMATION GEFSEC PROJECT ID: GEF AGENCY PROJECT ID: COUNTRY(IES): PROJECT TITLE: GEF AGENCY(IES): World Bank, OTHER EXECUTING PARTNER(S): GEF FOCAL AREA(S): International Waters, with benefits in Biodiversity GEF-3 STRATEGIC PRIORITIES: IW-1 AND B-2 GEF-4 STRATEGIC PROGRAM(S): IW-SP2; Component Four: Provides input to the RBMP Assure sustainability of investment
Component Four: Increased public participation in IWRM
Arrangements for results monitoring –
Target Values YR3 Annual meetings and training Data Collection and Reporting Frequency and Data Collection Responsibility for Reports Instruments Data Collection Annual reports PMT/PIT • PMT Quarterly and • Croatia: MAFWM Annual Reports, • BiH: MAFWM Supervision
Outcome Indicators Increased inter-state cooperation and capacity for transboundary water resource management Results Indicators for Each Component Component 1: Improved Transboundary water resource management of the Neretva and Trebisnjica River Basin Adoption of Transboundary River Basin Management Plan
Baseline Some capacity exists through ISWC
YR1 Annual meetings and training
YR2 Annual meetings and training
YR4 Annual meetings and training
YR5 Annual meetings and training
No plan exists
TOR, RFP and selection of consultant
Preparation of plan starts
Draft report
Final report and plan prepared
Adoption of the plan
Once every six months after the project effectiveness Semi-annually from effectiveness, seasonal reports once system is in place
PMT/PIT Quarterly and Annual Reports, Supervision Consultant status reports, later monitoring reports
• Croatia:MAFWM/ MPPCE • BiH: MAFWM /MOE • PMTs Drawn from implementation status reports of the Mostar and Trebinje PMT offices
Comprehensive hydrological measurement and monitoring program, linked to a transboundary water information system
Old hydrological data exist on waterflows and water quality
Updating of data, M&E and dissemination
Updating of data, M&E and dissemination
Updating of data, M&E and dissemination
Updating of data, M&E and dissemination
Updating of data, M&E, and dissemination
11
CEO Endorsement Template-Aug 29, 2007.doc
Component 2: Improved Management and Use of wetland ecosystems and biodiversity Environmental water flow requirements established and maintained through use of mathematical model for water management decision making Old requirements exist on water quality and flows Few samples are currently collected on water flow and quality Improved management of wetlands to better process pollutants, reduce outflow to international waterways and improve ecosystem health Restoration of water management infrastructure, including wetlands, river banks, and rehabilitation of Bunica river gate Poor management of wetland (quality and quantity) Preparation of TOR and RFP Preparation of Model starts Final Report and mathematical model prepared Environmental waterflows maintained Environmental waterflows maintained Semi-annual reports PMT/PIT Quarterly and Annual Reports, Supervision MAFWM / MPPCE / PMTs
Baseline updating
Improved sampling and dissemination of data
Improved sampling and dissemination of data
Improved sampling and dissemination of data
Improved pollutants processing and reduced outflow
Baseline updating
Studies carried out for improved management
Improved pollutants processing and reduced outflow
Improved pollutants processing and reduced outflow
Some data is available and documented in the EA
No plans implemented for restoration
Preparation of plans for restoration, including establishing key biodiversity database indicators in Hutovo Blato Nature Park TOR and RFP
Implementation of plans
Implementation of plans
Completion 80%
Some data is available and documented in the EA
Development of comprehensive plan for management of HPP reservoirs Area developed under the pilot scheme to mitigate salt intrusion in Neretva Delta (total area 400 ha)
No plan exists
Preparation of plan of plan Bidding
Final plan
Improved management of the reservoirs 200 ha completed
Improved management of the reservoirs 400 ha Completed.